Selection of sprayed time for permanent shotcrete based on evaluation of blasting vibration impact in deep-buried tunnels
Choosing appropriate time for the construction of the permanent shotcrete is a key subject in the New Austrian Tunneling Method (NATM), while the influence of blasting vibration on the shotcrete is an important influencing factor. For the blasting excavation of the 4# diversion tunnel in the Jinping-II Hydropower Station, dynamic responses of the shotcrete at different ages, which induced by the coupling action of blasting load and transient releasing of excavation load, are investicated with combined methods of the numerical simulation and the site monitoring. Results show that the shotcrete failure in blasting excavation of deep- buried tunnels is resulted from the coupling of the blasting load and the transient releasing of excavation load on high ground stress. The main failure mechanism is the shear failure mode. With regard to the shotcrete at different ages of 1 ~ 3 days, 3 ~ 7 days and 7 ~ 28 days, the safety distance from the tunnel face are 24 m, 13 m and 9 m respectively. The permanent shotcrete is suggested to be constructed behind the blasting face 6 excavation footage.
1. State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University,Wuhan,Hubei 430072,China;
2. Key Laboratory of Rock Mechanics in Hydraulic Structural Engineering Ministry of Education,Wuhan University,Wuhan,Hubei 430072,China
Abstract:Choosing appropriate time for the construction of the permanent shotcrete is a key subject in the New Austrian Tunneling Method (NATM), while the influence of blasting vibration on the shotcrete is an important influencing factor. For the blasting excavation of the 4# diversion tunnel in the Jinping-II Hydropower Station, dynamic responses of the shotcrete at different ages, which induced by the coupling action of blasting load and transient releasing of excavation load, are investicated with combined methods of the numerical simulation and the site monitoring. Results show that the shotcrete failure in blasting excavation of deep- buried tunnels is resulted from the coupling of the blasting load and the transient releasing of excavation load on high ground stress. The main failure mechanism is the shear failure mode. With regard to the shotcrete at different ages of 1 ~ 3 days, 3 ~ 7 days and 7 ~ 28 days, the safety distance from the tunnel face are 24 m, 13 m and 9 m respectively. The permanent shotcrete is suggested to be constructed behind the blasting face 6 excavation footage.
赵振国1,2,杨建华1,2,卢文波1,2,严 鹏1,2,陈 明1,2. 基于爆破振动影响评价的深埋隧洞围岩二次喷护时期选择[J]. 振动与冲击, 2015, 34(7): 8-14.
ZHAO Zhen-guo1,2,YANG Jian-hua1,2,LU Wen-bo 1,2,YAN Peng1,2,CHEN Ming1,2. Selection of sprayed time for permanent shotcrete based on evaluation of blasting vibration impact in deep-buried tunnels. JOURNAL OF VIBRATION AND SHOCK, 2015, 34(7): 8-14.
[1] 李晓红. 隧道新奥法及其量测技术[M]. 北京: 科学出版社, 2002.
[2] Lamis Ahmed, Anders Ansell. Structural dynamic and stress wave models for the analysis of shotcrete on rock exposed to blasting[J]. Engineering Structures, 2012(35): 11-17.
[3] 易长平. 爆破振动对地下洞室的影响[博士论文[D]. 武汉:武汉大学, 2005
[4] 陈明, 卢文波. 爆炸应力波对新浇混凝土衬砌的研究[J]. 岩土力学, 2008, 29(2): 455-459.
CHEN Ming, LU Wen-bo. The influence of explosive stress wave on young concrete lining[J]. Rock and Soil Mechanics, 2008, 29(2): 455-459.
[5] 李宁,陈蕴生. 爆破振动对衬砌损伤特性影响的室内试验研究[J]. 工程爆破, 1996, 2(2): 6-10.
LI Ning, CHEN Yun-sheng, HAN Xuan. Lab test on damage behavior of the tunnel lining under blasting load[J]. Engineering Blasting, 1996, 2(2): 6-10.
[6] 卢文波,周创兵,陈 明,等. 开挖卸荷的瞬态特性研究[J]. 岩石力学与工程学报,2008,27(11): 2184–2192.
LU Wenbo, ZHOU Chuangbing, CHEN Ming, et al. Research on transient characteristics of excavation unloading[J]. Chinese Journal of Rock Mechanics and Engineering, 2008, 27(11): 2184–2192.
[7] 孙金山,金李,姜清辉,等. 地下洞室爆破开挖过程中地应力瞬态调整诱发节理围岩松动机制研究[J]. 振动与冲击,2011,30(12):28–34.
SUN Jinshan, JIN Li, JIANG Qinhui, et al. Loosing mechanism of jointed rock mass induced by transient adjustment of in-situ stress[J]. Journal Of Vibration And Shock,2011,30(12):28–34.
[8] COOK M A, COOK U D, CLAY R B, et al. Behavior of rock duringblasting[J]. Transaction of Social Mining Engineering, 1966, (1): 17–25.
[9] CARTER J P, BOOKER J R. Sudden excavation of a long circular tunnel in elastic ground[J]. International Journal of Rock Mechanicsand Mining Sciences and Geomechanics Abstracts, 1990, 27(2): 129–132.
[10] 严 鹏,卢文波,陈明,等. TBM和钻爆开挖条件下隧洞围岩损伤特性研究[J]. 土木工程学报,2009, 42(11): 121-128.
Yan Peng, Lu Wenbo, Chen Ming, et al. Study of the damage character istics of surrounding rocks for tunnels constructed using TBM and drill-and- blast[J]. China Civil Engineering Journal, 2009, 42(11): 121-128.
[11] 严 鹏,卢文波,陈 明,等. 隧洞开挖过程初始地应力动态卸荷效应研究[J]. 岩土工程学报2009,12(31): 1888–1894.
Yan Peng, Lu Wenbo, Chen Ming, et al. Effect of initial geo-stress dynamic unloading during tunnel excavation[J]. Chinese Journal of Geotechnical Engineering, 2009, 31(12): 1888–1894.
[12] 严鹏,卢文波,许红涛. 高地应力条件下隧洞开挖动态卸荷的破坏机理初探[J]. 爆炸与冲击,2007,27(3): 283–287.
Yan Peng, Lu Wenbo, Xu Hongtao. A primary study to damage mechanism of initial stress dynamic unloading when excavating under high geostress condition[J]. Explosion and Shock Waves, 2007,27(3): 283–287.
[13] Lu Wenbo, Yang Jianhua, Chen Ming, Zhou Chuangbing. An Equivalent Method for Blasting Vibration Simulation.[J]. Simulation Modelling Practice and Theory. 2011,19(9):2050-2062.
[14] Jianhua Yang, Wenbo Lu, Ming Chen, Peng Yan, Chuangbing Zhou. Microseism induced by transient release of in-situ stress during deep rock mass excavation by blasting[J]. ROCK MECHANICS AND ROCK ENGINEERING , 2013,46(4): 859-875.
[15] Javier Toran˜o, Rafael Rodrı′guez, Isidro Diego, et al. FEM models including randomness and its application to the blasting vibrations prediction[J]. Computers and Geotechnics, 2006,33(1): 15-28.
[16] 杨建华,卢文波,陈明,等. 岩石爆破开挖诱发振动的等效模拟方法[J]. 爆炸与冲击, 2012, 32(2): 157-163.
YANG Jian-hua, LU Wen-bo, CHEN Ming, et al. An equivalent simulation method for blasting vibration of surrounding rock[J]. Explosion and Shock Waves, 2012, 32(2): 157-163.
[17] 陈士海,王明洋,赵跃堂,等. 岩石爆破破坏界面上的应力时程研究[J]. 岩石力学与工程学报,2003,22(11):1784–1788.
CHEN Shihai,WANG Mingyang,ZHAO Yuetang,et al. Time-stress historyon interface between cracked and uncracked zones under rockblasting[J]. Chinese Journal of Rock Mechanics and Engineering,2003,22(11):1784–1788.
[18] 卢文波,陶振宇. 爆生气体驱动的裂纹扩展速度研究[J]. 爆炸与冲击, 1994, 14(7).
LU Wen-bo, TAO Zhen-yu. Astudy of fracture propogation drived by gases of explosionproducts[J]. Explosion and Shock Waves, 1994, 14(7).
[19] 陈明祥. 弹塑性力学[M]. 北京: 科学出版社, 2007.
[20] Preece D S, Evans R & Richards A B.Coupled explosive gas flow and rock motion modeling with coMParison to bench blast field data[C].//Proc. 4th Int. Symp. Rock Fragmentation by Blasting. Vienna, Austria, 1993:239-246.
[21] 钟明寿,龙源,李兴华,等. 基于炮孔不同耦合介质的孔壁爆炸载荷及比能时间函数分析[J]. 振动与冲击, 2012, 30(7): 116-119.
ZHONG Ming-shou, LONG Yuan, LI Xing-hua, et al. Time function for borehole explosive loading and specific energy based on different coupling mediums[J]. Journal Of Vibration And Shock, 2012, 30(7): 116-119.
[22] 李洪涛,舒大强,卢文波,等. 建筑物对爆破振动中不同频率能量成分的响应特征[J]. 振动与冲击, 2010, 29(2): 154-158.
LI Hongtao, SHU Daqiang, LU Wenbo, et al. Response characteristics of a structure to differet frequency components in blasting vibration energy[J]. Journal Of Vibration And Shock, 2010, 29(2): 154-158.
[23] 卢文波,严鹏,杨建华,等.雅砻江锦屏二级水电站引水隧洞专题研究报告[R]. 2013,67-75.
[24] 中国工程爆破工程协会. GB6722–2011 爆破安全规程[S]. 北京: 中国标准出版社, 2011.